Typical Software Development Risks: Symptoms, Causes, Indicators, and Mitigations [From the Archives - First Published in 2012]

ScottGraffius_Com - From the Archives - Typical Software Development Risks and Mitigations - LwRes



black_spacer_lr_sq_v3

This article was first published on 16 December 2012.

black_spacer_lr_sq_v3

The risks for software development projects can vary. However, this article provides a view of the
typical risks along with the respective symptoms, root causes, leading indicators, and mitigations for each.

Risk: Inaccurate effort and estimates and schedules

  • Symptoms to watch for: Pattern of late deliverables; lack of awareness of schedule and status.
  • Potential root cause: Schedules based on business ('top down') need rather than team-generated ('bottom up').
  • Leading indicators: Earned value - schedule performance index (SPI).
  • Mitigations: 'Bottom up' planning; monitor effort and schedule; engage earned value for monitoring, control as needed.

Risk: Unconstrained requirements growth

  • Symptoms to watch for: Development staff cannot keep up with requirements changes.
  • Potential root cause: Requirements change not well-managed.
  • Leading indicators: Requirements change rate.
  • Mitigations: Plan for change (employ a requirements/change control process); don't start development until there is a stable set of requirements.

Risk: Dysfunctional organization

  • Symptoms to watch for: High project staff turnover; frequent staff reassignments; poor work environment; low productivity; staff lacks necessary skills and experience; and key role(s) are vacant.
  • Potential root cause: Lack of motivating work environment; poor management of project prioritization; lack of experience with work needed on project.
  • Leading indicators: Project staff turnover compared with historical trend; productivity; project team does not have an appropriate understanding of the requirements and project status.
  • Mitigation: Monitor, manage, and control issues and risks; status reporting; external (peer) assessment of project plans.

Risk: Poor software quality

  • Symptoms to watch for: High test defect counts; significant rework.
  • Potential root cause: Focus on schedule rather than quality.
  • Leading indicators: Test inspection yield; test defect density; defect discovery and closure rates/profiles.
  • Mitigation: Create a development quality plan that focuses on inspection rather than (only) test; measure and track against quality plan; cultivate a focus on software quality.

Risk: Under-performance

  • Symptoms to watch for: Low productivity.
  • Potential root cause: Technical complexity; development environment changes; under-achievement.
  • Leading indicators: Earned value - cost performance index (CPI).
  • Mitigation: Engaged earned value, control as needed.

Manage risks and you'll greatly improve the probability of success.

black_spacer_lr_sq_v3

How to Cite This Article

Graffius, Scott M. (2016, January 2). What Are Your Chances of Project Success? [From the Archives - First Published on 16 December 2012]. Available at:
https://scottgraffius.com/blog/files/archive---software-development-risks-and-mitigations.html.